New Building Project
General Information
Berea Makerspace has operated in a leased 2,500 sq ft facility at 116 Spring Circle Drive, Suite 3 since August 2019. The New Building Project (also referred to in planning notes as Makerspace 2.0) is the organization's multi-year effort to acquire and build out a permanent, larger, and more accessible workshop in central Berea.
Our current focus is the former Hicks Lumber property at 205 Lester Street in Berea. Moving into town reduces the need for a vehicle to reach the space, expands dedicated room for woodworking, metalworking, digital fabrication, and classes, adds studio and community-gathering space, and puts a long-vacant commercial lot back into productive community use.
For detailed meeting notes from 2022 through 2026, see New Building Meetings. For related governance decisions, see Board Meetings and Structure.
Site Overview: 205 Lester Street
| Detail | Information |
|---|---|
| Address | 205 Lester Street, Berea, KY 40403 |
| Parcel ID | B006-0006-0010 (Madison County PVA; New Berea Lots 5–13) |
| Lot Size | Approximately 0.67 acres (roughly 141' × 270') |
| Zoning | City of Berea B-2 (Commercial) |
| Former Use | Commercial lumberyard from the 1950s through 2014 (Hicks Lumber, 1991–2014); unoccupied since 2014 |
| Existing Structures | Three one-story structures totaling roughly 9,200 sq ft (a ~6,700 sq ft main building with ~4,500 sq ft enclosed and storm/roof damage, plus two open lean-tos of ~1,500 sq ft and ~1,000 sq ft) |
| Environmental Review | Kentucky Brownfield Program Targeted Site Assessment (Phase I) planned to evaluate existing conditions prior to renovation or demolition |
Planned Facility Layout
Layout plans are working concepts that will be refined based on environmental assessment results, City of Berea code requirements, and contractor estimates. Current planning focuses on the following zones:
- Wood Shop: Expanded woodworking area with a physically separated CNC Router room for dust and noise control, overhead and man doors, sink, compressed air, pallet-rack project storage, and a covered front awning.
- Metal Shop: Expanded welding, forging, and fabrication area with a physically separated CNC Plasma Table room, water access, compressed air, exterior propane hookup, overhead door, and a covered front awning.
- Clean Room and Digital Fabrication: Main public entrance, gathering and classroom space, ADA-accessible restroom(s), and an adjacent exhausted, sound-dampened area for lasers and 3D printers.
- Multi-Function Room: Flexible assembly and workshop room, kitchenette, and potential space for additional crafts such as ceramics.
- Artist Studios / Flex Rooms: Proposed 6 to 10 climate-controlled studio spaces (roughly 10' × 10' each) for working artists and makers.
- Outdoor Finishing Shed: Relocating the existing ventilated paint and stain finishing shed outside the main buildings for safety and insurance compliance.
Planners are evaluating separate metal shop buildings connected by covered awnings (to separate dust, noise, fire risk, and HVAC) alongside whether any existing concrete pads or lean-to structures on the lot can be reused. Longer-term ideas noted for future phases or partner grants include solar and energy-efficiency upgrades with Mountain Association, native landscaping, a community tool library, a sawmill/wood-drying area, and a shared commercial kitchen.
Site Plans and Conceptual Layouts
-
Makerspace 2.0 conceptual floor plan (Wood Shop, Metal Shop, Main Building)
-
Conceptual layout overlaid on the 205 Lester Street lot
-
205 Lester Street half-lot footprint diagram (5,000 sq ft initial + 2,500 sq ft future)
-
City of Berea zoning map showing 205 Lester Street in B-2 zone
Additional plat sketches, lot measurements, and parking diagrams are archived on New Building Meetings.
Project Timeline
| Period | Milestone |
|---|---|
| 2022–2023 | Explored relocating to the former Poke Boat building on Broadway, including layout planning and pre-construction meetings. After that option did not move forward, members evaluated other commercial properties around Berea. |
| 2024 | Worked with grant consultant Robin Taffler on community-impact narrative, outreach strategy, and partner alignment; began evaluating the Lester Street lumberyard property. |
| Late 2025 | Board members and community partners toured 205 Lester Street to assess existing structures, lot layout, and shared community-use possibilities. |
| Early 2026 | Held layout and planning meetings (February and April 2026) to define shop zones, code and parking requirements, and conceptual Makerspace 2.0 footprints; prepared a Kentucky Brownfield Program Targeted Site Assessment (Phase I) application. |
| May–November 2026 | Board passed a resolution authorizing an Option to Purchase Real Estate agreement for 205 Lester Street (May 2026) and reviewed amended option terms incorporating brownfield assessment access (August–October 2026); the option agreement has not yet been signed. Organizational readiness and financing work—including USDA Community Facilities loan preparation—are ongoing. |
How to Get Involved
This is a volunteer-led effort and welcomes input from members and community partners.
- Join the #new-building channel on Slack for ongoing updates and layout discussions.
- Attend open board and building planning meetings listed on Meetings and announced in Slack.
- Reach out at info@bereamakerspace.org if you can help with shop layout planning, construction/contractor estimates, grant research, or community partnerships.
- Support Berea Makerspace directly at bereamakerspace.org/donate.